IMAGE PLANT, PALAKKAD
The plant is situated in the midst of 25 acres of land. There are 5 main buildings & few small buildings for the plant with a total plinth area more than 97958.22 sq.ft
Buildings
- ) Incinerator Plant Buildings (Plant I, II & III)
- ) Autoclave Plant Building
- ) Discarded Medicine Shed
- ) Processed Red Waste Sorting Plant
- ) Processed Scrap Storage Shed
- ) Ash Storage Shed
- ) Effluent Treatment Building
- ) Sewage treatment Plant
- ) Bottle Processing Unit
- ) Canteen
- ) Office Buildings
- ) Conference Hall
- ) Security and Office
- ) Staff Rest Area
- ) Vehicles washing area
- ) Cloak Room
Installed Equipment & Capacity in IMAGE Plant
Incinerators
|
(Unit) |
(Capacity) |
Incinerator 1 (Rotary) |
1 No. |
750 Kg/hr |
Incinerator 2 (Static) |
1 No. |
250 Kg/hr |
Incinerator 3 (Static) |
1 No. |
250 Kg/hr |
Incinerator 4 (Rotary) |
1 No. |
500 Kg/hr |
Incinerator 5 (Static) |
1 No. |
250 Kg/hr |
Total Incinerable Capacity of is 2000 Kg/Hr. The plant is working 24 hours per day. The daily incinerable capacity of the incinerators is 48 tones per day.
Autoclaves
High Pressure Sterilizer 5 Nos. Out of which, 2 of them are 1000 Ltrs Capacity (approx. 100kgs) each and 3 of them is 3000 Ltrs capacity (approx. 300 kgs) per cycle. We can operate 24 cycles per day in these autoclaves. The total daily autoclavable capacity is 26 tonnes per day.
Effluent Treatment Plant (ETP)
4.5 Lakhs Litres per day
Other Essential Utilities & Equipment in the plant are
- ) Fuel storage tank
- ) Bore wells and Pump
- ) Effluent Treatment Plant
- ) Sewage Treatment Plant
- ) 380 KVA Generator
- ) 400 KVA Generator (Standby Generator)
- ) Ash storage and handling area
- ) Weighing Machines
- ) Transformers
- ) Chimneys of 30 Mtr height
- ) Hydraulic bundling machines
- ) Scrap grinders
- ) Bottle sorting machines
- ) Conveyor belt system
- ) Rain water harvest
- ) CCTV Camera with Recorders